Measurement of wall thickness, VOC catalytic combustor
WTE was appointed by MATEC to verify the equipment status of medical waste incineration plant after a destructive explosion occurred during first start up. The plant was located in Paderno Dugnano. Major damages on boiler and gas cleaning system were recorded. After the analysis WTE was designated to deliver the general project of the revamping …
Engineering for revamping of hospital waste plant Read More »
The GPC Gruppo Public Consult Spa committed to W.T.E. the expediting and the vendor compliance audit during the manufacturing of a steam boiler of 20 tons/hour to be installed on the third line of the waste to energy plant sited in Schio (Italy).
CON.SER.VCO, the owner of the incineration plant sited in Mergozzo (VCO), needed a detailed report on the actual state of the refractory lining in the furnaces. W.T.E. delivered an objective analysis about the conditions of furnace walls and some suggestions concerning maintenance and refurbishment costs .