Feasibility study for a biomass boiler revamping and for new thermal cycle

Silvateam Group is an Italian holding,  world leader in the production of plant base extracts, since 1854. The job assigned included the study of biomass boiler revamping to improve steam characteristics and combustion, a new thermal cycle, a new gas cleaning system and a new biomass drying system.          

construction supervision

Engineering and permitting services-357/15

Engineering services to receive GSE approval of the project related to a new cogenerative biomass to energy plant with of capacity 2.4 MWe . The plant would have been fed with residues of wood treatment produced in the main industrial process owned by Florian Legno Spa

Consulting on operational procedures

W.T.E. updated all operational procedures, start-up, emergency shutdown procedures, etc. for each section of the Geofor Spa Incineration plant -Ospedaletto (Pisa).

Assessment of the solar thermal input to the electricity’s amount supplied by biomass plant

ECOSESTO SpA  appointed W.T.E. to assess the contribute of solar heat supplied to a conventional Rankine cycle in terms of delivered electric energy . A proper evaluation was required in order to obtain the corresponding fee from GSE, Italian energy Authority. Considering the inertion of solar heat at lower  temperature than those used in biomass …

Assessment of the solar thermal input to the electricity’s amount supplied by biomass plant Read More »

engineering for permitting

Engineering and permitting services

Luino Energia Srl commissioned several engineering activities to W.T.E. in order to receive permit for the erection of a biomass plant near the city of Luino. Main plant parameters: 100% MCR – 8.9 MWth – electric power at generator terminal 2.38 MWe. Scope of work included: – verifying the expected energy efficiency; – defining the …

Engineering and permitting services Read More »

consulting engineering

Engineering services for two Turbogas plants

W.T.E. provided engineering services to E.s.e. Srl in order to support this client in evaluating Air Condensers to be installed on two Combined Cycle Power Plant in Middle East countries.