Failure analysis of MSW mechanical treatment system
Analysis of failures in MSW preselection screens and belt conveyors; Milano Zama facility
Analysis of failures in MSW preselection screens and belt conveyors; Milano Zama facility
IBI Spa ordered to W.T.E. the development of complete engineering of the air treatment system (reactor and Venturi) to be installed on the MSW incineration plant, owned by CASIC, in Cagliari.
Progetto di rifacimento del sistema di depurazione fumi esistente (portata fumi 25.000 Nm3/h) sul termovalorizzatore a letto fluido di Macomer (NU). Ingegneria di base completa di specifiche tecniche per la realizzazione di due filtri a maniche, di due sistemi in circuito chiuso di preriscaldo e di bypass fumi, del sistema di estrazione/scarico ceneri, degli strumenti …
Basic engineering for gas cleaning system, EfW Plant, Macomer (NU) Read More »
W.T.E. provided the on-line cleaning of line 1 of the boiler installed on the incineration plant managed by AGSM VERONA , by the Bang & Clean system.
Preliminary design and technical specification write-up for a new SCR DeNOx system and replacement of the existing dry lime system with a new sodium bicarbonate one, AMSA Milano “Silla 2” MSW incineration plant
From 2002 to 2005 W.T.E. provided to M.E.T.A. Spa many interventions of ordinary maintenance of the furnace-boiler system . These maintenance operations were realised on the three lines of the waste to energy plant sited in Modena. Maintenance services included: cleaning on line by Bang & Clean system of boilers and degasers; Measurement of wall …
“Major improvements to the thermal cycle, AAMPS Livorno MSW incineration plant.
On-line cleaning of line 1 boiler installed on the MSW incineration plant in Ravenna, managed by Ecologia Ambiente SpA.
FUEL TECH Engineering ordered to W.T.E. the complete project, the construction and transport of two urea-NH3 reactors to be installed on a MSW incineration plant, Brest (France)
TECNOCASIC had to realise the revamping of MSW incineration plant located in Cagliari neirbourough in order to comply with environmental Italian law. Main sections of plants were replaced after new design of all the system. W.T.E. was required to deliver the basic engineering, thermodimanic calculation of new process, and detailed engineering for the reconstruction of …
Engineering for revamping of furnaces on MSW incineration plant Read More »