Activity: Engineering

Incineration plant tail end boiler

Engineering of new cooling towers

W.T.E. designed a new lay out of wte cooling towers, also delivering structural design of related reinforced concrete platform. Client: A.Am.P.S. Spa Livorno

Study of a sludge drying system to substitute coal in an utility boiler.

A feasibility study was carried out to evaluate, both form economic and technical point of view, the possibility to dry organic and industrial slurry to feed the 51.7 MWth coal boiler as an alternative to coal. Mascioni Spa, co-generative power station, Cuvio (VA) Some plant figures: -Maximum Continuous Rate (MCR): 51.7 MW -Maximum gross power …

Study of a sludge drying system to substitute coal in an utility boiler. Read More »

Flue gas cleaning system dimensioning

Basic engineering

W.T.E. studied and delivered to Hascon Engineering the dimensioning of a spray dryer and technical specifications of washing towers to be provided to foreign client.

software for boiler fouling prediction

Predictive monitoring of boiler fouling

Development of a software for the predictive monitoring of boiler fouling to: adjust in real-time of the soot blowing cycles predict concretions and build-up schedule plant downtime for cleaning operation W.T.E. provided software to process boiler bundles thermodynamic data in order to advice operators about fouling.

combustion diagram 60 MWth

Engineering for permitting

Actelios Spa, company owned by Falck Renewables Spa, commissioned to W.T.E. Waste To Energy the design of a biomass cogeneration plant with 17 MWe-60 MWth capacity. Scope of the work was to obtain  permitting named AIA and VIA from public authorities in Torremaggiore (FG) The high efficiency power plant would be fed by lignocellulosic biomass …

Engineering for permitting Read More »

Feasibility study of installation of booster fans, wte plant in Macomer

Modifications of existing lines, with installation of booster fans W.T.E. was ordered to deliver a feasibility study of the upgrade of booster fans allowing the discharge of combustion fumes, one fan for each line of the incineration plant with fluidised bed technology in Macomer. In the project  the new fans are placed before the existing …

Feasibility study of installation of booster fans, wte plant in Macomer Read More »